CLIENT
Rhomberg Sersa
Infrastructure
Network Rail
Delivery period
February 2023
Project Overview
CTS was engaged to deliver the prefabrication and installation of FFU bearers within the wash road at Stewarts Lane Depot. The works were undertaken during a tightly controlled 52-hour possession, requiring coordinated prefabrication and efficient on-site installation.

Project Scope
- Prefabrication of 50m of FFU bearers, including pre-installation of baseplates and rail
- Installation and alignment of new FFU bearers
- Installation of formwork and temporary works
- Mixing, pumping, and placement of approximately 20m³ of grout

Delivery
Through off-site prefabrication and detailed planning, CTS minimised on-site installation time and ensured precise track alignment within the possession window. All works were completed safely and handed back in accordance with programme requirements.